Once you've completed installation of your test article, follow these steps when ready to power-up the tunnel.

Note that this checklist only covers baseline operation of the tunnel itself and the air flow meter. The operation of any other equipment is regarded as experiment-specific and thus should be covered in its own checklist.

hashtag
Prepare the space

hashtag
Prepare the instruments

circle-info

If the FlowKinetics was already on when you entered, you may want to consider power cycling it and re-calibrating to account for any changes to ambient conditions.

hashtag
Power on the tunnel

hashtag
Wind Tunnel Shutdown Procedure

Make sure there are no pieces of tape that have come undone during the previous usage.
  • On the fan control panel, set the control dial to 20% of maximum power

  • Turn off the master breaker switch
  • Venkat Putchaenvelope